§47110. Allowable project costs
(a)
(b)
(1)(A) if the cost necessarily is incurred in carrying out the project in compliance with the grant agreement made for the project under this subchapter, including any cost a sponsor incurs related to an audit the Secretary requires under section 47121(b) or (d) of this title and any cost of moving a Federal facility impeding the project if the rebuilt facility is of an equivalent size and type; or
(B) if the cost is an incentive payment incurred in carrying out the project described in subparagraph (A) that is to be provided to a contractor upon early completion of a project, if-
(i) such payment does not exceed the lesser of 5 percent of the initial construction contract amount or $1,000,000;
(ii) the level of contractor's control of, or access to, the worksite necessary to shorten the duration of the project does not negatively impact the operation of the airport;
(iii) the contract specifies application of the incentive structure in the event of unforeseeable, non-weather delays beyond the control of the contractor;
(iv) nothing in any agreement with the contractor prevents the airport operator from retaining responsibility for the safety, efficiency, and capacity of the airport during the execution of the grant agreement; and
(v) the Secretary determines that the use of an incentive payment is likely to increase airport capacity or efficiency or result in cost savings as a result of shortening the project's duration;
(2)(A) if the cost is incurred after the grant agreement is executed and is for airport development or airport planning carried out after the grant agreement is executed;
(B) if the cost is incurred after June 1, 1989, by the airport operator (regardless of when the grant agreement is executed) as part of a Government-approved noise compatibility program (including project formulation costs) and is consistent with all applicable statutory and administrative requirements;
(C) if the Government's share is paid only with amounts apportioned under paragraphs (1) and (2) of section 47114(c) or section 47114(d)(3)(A) 1 and if the cost is incurred-
(i) after September 30, 1996;
(ii) before a grant agreement is executed for the project; and
(iii) in accordance with an airport layout plan approved by the Secretary and with all statutory and administrative requirements that would have been applicable to the project if the project had been carried out after the grant agreement had been executed; or
(D) if the cost is for airport development and is incurred before execution of the grant agreement, but in the same fiscal year as execution of the grant agreement, and if-
(i) the cost was incurred before execution of the grant agreement because the airport has a shortened construction season due to climatic conditions in the vicinity of the airport;
(ii) the cost is in accordance with an airport layout plan approved by the Secretary and with all statutory and administrative requirements that would have been applicable to the project if the project had been carried out after execution of the grant agreement, including submission of a complete grant application to the appropriate regional or district office of the Federal Aviation Administration;
(iii) the sponsor notifies the Secretary before authorizing work to commence on the project;
(iv) the sponsor has an alternative funding source available to fund the project; and
(v) the sponsor's decision to proceed with the project in advance of execution of the grant agreement does not affect the priority assigned to the project by the Secretary for the allocation of discretionary funds;
(3) to the extent the cost is reasonable in amount;
(4) if the cost is not incurred in a project for airport development or airport planning for which other Government assistance has been granted;
(5) if the total costs allowed for the project are not more than the amount stated in the grant agreement as the maximum the Government will pay (except as provided in section 47108(b) of this title);
(6) if the cost is for a project not described in section 47102(3) for acquiring for use at a commercial service airport vehicles and ground support equipment owned by an airport that include low-emission technology, but only to the extent of the incremental cost of equipping such vehicles or equipment with low-emission technology, as determined by the Secretary; and
(7) if the cost is incurred on a measure to improve the efficiency of an airport building (such as a measure designed to meet one or more of the criteria for being considered a high-performance green building as set forth under section 401(13) of the Energy Independence and Security Act of 2007 (42 U.S.C. 17061(13))) and-
(A) the measure is for a project for airport development;
(B) the measure is for an airport building that is otherwise eligible for construction assistance under this subchapter; and
(C) if the measure results in an increase in initial project costs, the increase is justified by expected savings over the life cycle of the project.
(c)
(1) necessarily incurred in formulating or preparing for an airport development project, including costs incurred for field surveys, plans and specifications, property interests in land or airspace, utility relocation, work site preparation, and administration or other incidental items that would not have been incurred except for the project; or
(2) necessarily and directly incurred in developing the work scope of an airport planning project.
(d)
(1) the Government's share of such costs will be paid with funds apportioned to the airport sponsor under section 47114 or distributed from the small airport fund under section 47116;
(2) the Secretary determines that the relocation or replacement is required due to a change in the Secretary's design standards; and
(3) the Secretary determines that the change is beyond the control of the airport sponsor.
(e)
(2) Paragraph (1) of this subsection applies to a project-
(A) about which the sponsor notifies the Secretary, before the project begins, of the sponsor's intent to carry out the project;
(B) that will comply with all statutory and administrative requirements that would apply to the project if it were carried out with amounts made available under this subchapter; and
(C) that meets the criteria of section 47115(d) and, if for a project at a medium hub airport or large hub airport, the Secretary decides will enhance system-wide airport capacity significantly.
(3) A letter of intent issued under paragraph (1) of this subsection is not an obligation of the Government under section 1501 of title 31, and the letter is not deemed to be an administrative commitment for financing. An obligation or administrative commitment may be made only as amounts are provided in authorization and appropriation laws.
(4) The total estimated amount of future Government obligations covered by all outstanding letters of intent under paragraph (1) of this subsection may not be more than the amount authorized to carry out section 48103 of this title, less an amount reasonably estimated by the Secretary to be needed for grants under section 48103 that are not covered by a letter.
(5)
(6)
(7)
(A) the application was approved in fiscal year 2019; and
(B) the project meets all other requirements set forth in this chapter.
(f)
(1) constructing a public parking facility for passenger automobiles;
(2) constructing, altering, or repairing part of an airport building, except to the extent the building will be used for facilities or activities directly related to the safety of individuals at the airport;
(3) decorative landscaping; or
(4) providing or installing sculpture or art works.
(g)
(h)
(i)
(1)
(2)
(3)
(A) the Government's share of allowable project costs; or
(B) $10,000,000.
(4)
(5)
(A) the sponsor notifies the Secretary, before the project begins, of the intent of the sponsor to carry out the project and requests a letter of intent; and
(B) the sponsor agrees to comply with all statutory and administrative requirements that would apply to the project if it were carried out with amounts made available under this subchapter.
(6)
(7)
(A) prioritize projects that-
(i) cannot reasonably be funded by an airport sponsor using funds apportioned under section 47114(c), 47114(d)(2)(A), or 47114(d)(6), including funds apportioned under such sections in multiple fiscal years pursuant to section 47117(b)(1); and
(ii) are necessary to the continued safe operation or development of an airport; and
(B) structure the reimbursement schedules under such letters in a manner that minimizes unnecessary or undesirable project segmentation.
(8)
(A)
(B)
(9)
(
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
47110(a) | 49 App.:2212(a) (1st, last sentences). | Sept. 3, 1982,
|
47110(b) | 49 App.:2212(a) (2d sentence cls. (1), (2) (words before period), (3), (4)). | |
47110(c) | 49 App.:2212(a) (2d sentence cl. (2) (words after period)). | |
47110(d) | 49 App.:2212(b)(1), (6). | Sept. 3, 1982,
|
47110(e) | 49 App.:2212(d). | Sept. 3, 1982,
|
47110(f) | 49 App.:2212(c). | Sept. 3, 1982,
|
In subsection (a), the words "for airport development or airport planning" are omitted because of the definition of "project" in section 47102 of the revised title. The text of 49 App.:2212(a) (last sentence) is omitted as surplus because of 49:322(a).
In subsection (b)(1), the word "approved" is omitted as surplus because a project that was not approved could not be carried out in compliance with a grant agreement. The words "in compliance with the grant agreement made for the project under this subchapter" are substituted for "in conformity with the terms and conditions of the grant agreement entered into in connection with the project" to eliminate unnecessary words. The word "sponsor" is substituted for "recipient" for clarity.
In subsection (b)(2)(A), the words "with respect to the project" are omitted as unnecessary because "the grant agreement" means "the grant agreement made for the project" referred to in clause (1) of this subsection. The words "under the project" are omitted as surplus.
Subsection (b)(3) is substituted for "in the opinion of the Secretary it is reasonable in amount, and if the Secretary determines that a project cost is unreasonable in amount, the Secretary may allow as an allowable project cost only so much of such project cost as the Secretary determines to be reasonable" to eliminate unnecessary words.
Subsection (b)(5) is substituted for "except that in no event may the Secretary allow project costs in excess of the definite amount stated in the grant agreement except to the extent authorized by section 2211(b) of this Appendix" for consistency in this section.
In subsection (c), before clause (1), the words "The Secretary may decide that a project cost . . . is allowable" are substituted for "However, the allowable costs of a project . . . may include . . . and the allowable costs of a project . . . may include" for clarity and consistency in the revised title. The words "incurred after May 13, 1946, and before the date the grant agreement is executed" are substituted for "which were incurred prior to the execution of the grant agreement and subsequent to May 13, 1946" and "which were incurred subsequent to May 13, 1946" to eliminate unnecessary words. In clause (1), the words "preparation of", "acquisition of", "by the sponsor specifically in connection with the accomplishment of the project for airport development" are omitted as surplus. The words "property interests in land or airspace" are substituted for "land or interests therein or easements through or other interests in airspace" to eliminate unnecessary words.
In subsection (d)(1), before clause (A), the words "The Secretary may decide that the cost . . . is allowable" are substituted for "the Secretary may approve, as allowable project costs" and "The Secretary shall approve project costs allowable under paragraph (1) of this subsection" for clarity and consistency in this section. In clause (B), the words "the boundaries of" are omitted as surplus. In clause (C), the words "and conditions" are omitted as being included in "terms".
In subsection (d)(2), the words "In making a decision under paragraph (1) of this subsection, the Secretary may approve as allowable costs" are substituted for "In the case of a commercial service airport . . . the Secretary may approve, under the preceding sentence as allowable project costs" for consistency in this subsection.
In subsection (e)(1), the word "sponsor" is substituted for "applicant" for consistency. The words "stipulated as" and "Subject to the provisions of this paragraph" are omitted as surplus. The word "reimburse" is substituted for "make payments under paragraph (2) of this subsection" and "pay" for clarity. The words "payable on account of such project in accordance with such letter of intent" are omitted as surplus.
In subsection (e)(2), before clause (A), the text of 49 App.:2212(d)(1)(C) (last sentence) is omitted as obsolete.
In subsection (e)(3), the words "A letter of intent issued" are substituted for "action" for clarity. The word "deemed" before "an obligation" is omitted as surplus.
In subsection (f)(2), the words "of a hangar or" are omitted as being included in "airport building".
Pub. L. 103–429
The source credits for all of subsection (b) are included for clarity though only subsection (b)(2) is affected by the amendment. The source credits for 49:47110(c) are included to correct a mistake on p. 405 of H. R. Rept. 103–180 (103d Cong., 1st Sess., July 15, 1993).
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
47110(b) | 49 App.:2212(a) (2d sentence cls. (1), (2)(A) (words before period), (B), (3), (4)). | Sept. 3, 1982, |
47110(c) | 49 App.:2212(a) (2d sentence cl. (2)(A) (words after period). |
In subsection (b)(2)(C)(ii), the words "before the cost is incurred" are added for clarity.
Editorial Notes
References in Text
Section 47114(d)(3)(A), referred to in subsecs. (b)(2)(C) and (g), was redesignated section 47114(d)(2)(A) by
Amendments
2024-Subsec. (c).
Subsec. (c)(1).
Subsec. (d)(1).
Subsec. (e)(2)(C).
Subsec. (e)(7).
Subsec. (h).
Subsec. (i).
2022-Subsec. (b)(1).
Subsec. (e)(7).
2018-Subsec. (b)(2)(B).
Subsec. (b)(2)(D)(i).
Subsec. (e)(7).
2012-Subsec. (b)(2)(D).
Subsec. (b)(7).
Subsec. (d).
Subsec. (e)(5).
Subsec. (h).
Subsec. (i).
2005-Subsec. (d)(2)(A).
2003-Subsec. (b)(1).
Subsec. (b)(2)(C).
Subsec. (b)(6).
Subsec. (g).
Subsec. (h).
2001-Subsec. (b)(2)(D).
2000-Subsec. (e)(2)(C).
Subsec. (e)(5).
1996-Subsec. (b)(2)(C).
"(i) during the fiscal year ending September 30, 1994;
"(ii) before a grant agreement is executed for the project but according to an airport layout plan the Secretary approves before the cost is incurred and all applicable statutory and administrative requirements that would apply to the project if the agreement had been executed; and
"(iii) for work related to a project for which a grant agreement previously was executed during the fiscal year ending September 30, 1994;".
Subsec. (g).
1994-Subsec. (b)(2).
"(A) after the grant agreement is executed and is for airport development or airport planning carried out after the grant agreement is executed; or
"(B) after June 1, 1989, by the airport operator (regardless of when the grant agreement is executed) as part of a Government-approved noise compatibility program (including project formulation costs) and is consistent with all applicable statutory and administrative requirements;".
Subsec. (e)(6).
Statutory Notes and Related Subsidiaries
Effective Date of 2003 Amendment
Amendment by
Effective Date of 2000 Amendment
Amendment by
Effective Date of 1996 Amendment
Except as otherwise specifically provided, amendment by
Letters of Intent for Airport Security Improvement Projects
"(a) The Under Secretary of Transportation for Security [now Administrator of the Transportation Security Administration] may issue a letter of intent to an airport committing to obligate from future budget authority an amount, not more than the Federal Government's share of the project's cost, for an airport security improvement project (including interest costs and costs of formulating the project) at the airport. The letter shall establish a schedule under which the Under Secretary will reimburse the airport for the Government's share of the project's costs, as amounts become available, if the airport, after the Under Secretary issues the letter, carries out the project without receiving amounts under Chapter 471 of title 49 [United States Code].
"(b) The airport shall notify the Under Secretary of the airport's intent to carry out the airport security improvement project before the project begins.
"(c) A letter of intent may be issued under this section only if-
"(1) The airport security improvement project to which the letter applies involves the replacement of baggage conveyer systems or the reconfiguration of terminal baggage areas in order to install explosive detection systems; and
"(2) The Under Secretary determines that the project will improve security or will improve the efficiency of the airport without lessening security.
"(d) A letter of intent issued under this section is not an obligation of the Government under section 1501 of title 31 [United States Code], and the letter is not deemed to be an administrative commitment for financing. An obligation or administrative commitment may be made only as amounts are provided in authorization and appropriations laws.
"(e) The Government's share of the project's cost shall be 75 percent for a project at an airport having at least 0.25 percent of the total number of passenger boardings each year at all airports and 90 percent for a project at any other airport.
"(f) Nothing in this section shall be construed to prohibit the obligation of amounts pursuant to a letter of intent under this section in the same fiscal year as the letter of intent is issued.
"(g) The Under Secretary shall notify the House and Senate Committees on Appropriations, the House Transportation and Infrastructure Committee, and the Senate Commerce, Science, and Transportation Committee at least 3 days prior to the issuance of a letter of intent under this section.
"(h) There is authorized to be appropriated to carry out this section $500,000,000 in each of fiscal years 2003, 2004, 2005, 2006, and 2007."
Letters of Intent; Duration of Authority and Approval by Congress