§8669c. Assessments required prior to start of construction on first ship of a shipbuilding program
(a)
(1) submits a report to the congressional defense committees on the results of any production readiness review;
(2) certifies to the congressional defense committees that the findings of any such review support commencement of construction; and
(3) certifies to the congressional defense committees that the basic and functional design of the vessel is complete.
(b)
(1) The maturity of the ship's design, as measured by stability of the ship contract specifications and the degree of completion of detail design and production design drawings.
(2) The maturity of developmental command and control systems, weapon and sensor systems, and hull, mechanical and electrical systems.
(3) The readiness of the shipyard facilities and workforce to begin construction.
(4) The Navy's estimated cost at completion and the adequacy of the budget to support the estimate.
(5) The Navy's estimated delivery date and description of any variance to the contract delivery date.
(6) The extent to which adequate processes and metrics are in place to measure and manage program risks.
(c)
(1)
(A) fixes the major hull structure of the vessel;
(B) sets the hydrodynamics of the vessel; and
(C) routes major portions of all distributive systems of the vessel, including electricity, water, and other utilities.
(2)
(A) the ship is the first ship to be constructed under that shipbuilding program; or
(B) the shipyard at which the ship is to be constructed has not previously started construction on a ship under that shipbuilding program.
(3)
(4)
(5)
(Added