§4422. Weapon system component or technology prototype projects: oversight
(a)
(b)
(1) expertise in requirements; research, development, test, and evaluation; acquisition; sustainment; or other relevant areas within the military department concerned;
(2) awareness of technology development activities and opportunities in the Department of Defense, industry, and other sources; and
(3) awareness of the component capability requirements of major weapon systems, including scheduling and fielding goals for such component capabilities.
(c)
(1) To issue a strategic plan every three years that prioritizes the capability and weapon system component portfolio areas for conducting prototype projects, based on assessments of-
(A) high priority warfighter needs;
(B) capability gaps or readiness issues with major weapon systems;
(C) opportunities to incrementally integrate new components into major weapon systems based on commercial technology or science and technology efforts that are expected to be sufficiently mature to prototype within three years; and
(D) opportunities to reduce operation and support costs of major weapon systems.
(2) To annually recommend funding levels for weapon system component or technology development and prototype projects across capability or weapon system component portfolios.
(3) To annually recommend to the service acquisition executive of the military department concerned specific weapon system component or technology development and prototype projects, subject to the requirements and limitations in section 4423 of this title.
(4) To ensure projects are managed by experts within the Department of Defense who are knowledgeable in research, development, test, and evaluation and who are aware of opportunities for incremental deployment of component capabilities and other technologies to major weapon systems or directly to support warfighting capabilities.
(5) To ensure projects are conducted in a manner that allows for appropriate experimentation and technology risk.
(6) To ensure projects have a plan for technology transition of the prototype into a fielded system, program of record, or operational use, as appropriate, upon successful achievement of technical and project goals.
(7) To ensure necessary technical, contracting, and financial management resources are available to support each project.
(8) To submit to the congressional defense committees a semiannual notification that includes the following:
(A) each weapon system component or technology prototype project initiated during the preceding six months, including an explanation of each project and its required funding.
(B) the results achieved from weapon system component prototype and technology projects completed and tested during the preceding six months.
(Added
Editorial Notes
Amendments
2021-
Subsec. (c)(3).
Statutory Notes and Related Subsidiaries
Effective Date of 2021 Amendment
Amendment by
Effective Date
Section effective Jan. 1, 2017, see section 806(a)(2) of